Soluna reports October construction at Dorothy 3. The 50 MW IT first phase retains JV and lease conditions, with fiber studies complete and 21 operating jobs forecast.
Soluna says construction work began at its Dorothy 3 AI data-center campus in October, moving the Briscoe County, Texas development into a new stage. Its November 16 business update also reports October work at Kati 2 in Willacy County. For contractors, the change makes project-team identification, underground coordination and package timing more relevant. The evidence still leaves important questions about the extent of field work and the agreements supporting delivery.
Dorothy 3A, the first phase, remains a planned 50 MW critical IT facility with approximately 75 MW gross capacity. The Applied Digital joint venture has closing conditions, and prospective tenant ChronoScale has a nonbinding letter of intent. LVN reviewed the owner update, prepared remarks, investor presentation, SEC filings and related Texas registration. This November 17 refresh preserves those distinctions. The featured artwork is an AI-generated concept illustration; it does not document actual site progress.
What changed at Dorothy 3
The owner’s construction announcement is a material update to the earlier development picture. Soluna previously disclosed land acquisition, planning and procurement activity. It now identifies October as the month construction began. The reviewed material does not supply an exact start day, independently inspected building permit or detailed account of Dorothy’s vertical work. A contractor should request current issued drawings and a site-specific scope before treating this announcement as an invitation to bid.
| Item | Current evidence | Qualification |
|---|---|---|
| Location | Briscoe County, near Silverton | 397-acre campus |
| Construction | October start reported | Owner account; extent unverified |
| First phase | 50 MW IT / about 75 MW gross | Planned Dorothy 3A |
| Joint venture | Applied 51% / Soluna 49% | Ownership at closing |
| Tenant | ChronoScale | Nonbinding LOI |
| Operating jobs | About 21 full-time | Owner’s Phase 1 forecast |
The prepared remarks describe completed environmental, water, survey and fiber studies, alongside master planning and long-lead procurement. Those studies can inform route selection and coordination. Their completion alone establishes neither installed carrier infrastructure nor an awarded fiber contract. The same remarks identify future lease and ready-for-service milestones without committed delivery dates.
The transaction still has conditions
Soluna’s November 16 Form 10-Q describes the October 20 subscription agreement. At closing, Applied affiliates would hold 51% and Soluna 49% of the project company. The filing targets December 1, with extension possible through December 31. These dates concern the transaction. A public facility-opening date has not been established.
The filing reports that the county tax-abatement condition was satisfied November 9. LVN has not independently inspected the county minutes. Other transaction conditions, including title and final documents, remain relevant. The contemplated roughly $19.5 million Applied cash contribution carries credits for qualifying earlier expenditures; Soluna’s ground-sublease contribution has an attributed value of roughly $18.8 million. Neither number represents the total construction budget or verified funding received.
The subscription agreement names Hypergate LLC as a contemplated EPC counterparty and identifies Lighthouse Electric Cooperative and Briscoe Wind in power-agreement conditions. Those references provide useful diligence leads. An executed EPC agreement, specialty subcontract, firm delivery schedule and complete power-service scope were not established in this review. Hypergate’s public website remains unresolved, so similarly named businesses should not be substituted.
Who is connected, and in what role
Company relationships are most useful when their limits are clear. Applied Digital is the prospective majority joint-venture partner. ChronoScale is the prospective tenant. Neither role identifies the contractor buying structured cabling, security or controls work. The owner, project company, tenant and eventual prime contractor may each control different interfaces.
| Organization | Documented relationship | Limit |
|---|---|---|
| Soluna | Campus developer | Phase 1 JV pending |
| Applied Digital | Prospective 51% partner | Closing conditions remain |
| ChronoScale | Prospective tenant | LOI; lease pending |
| Hypergate LLC | Contemplated EPC party | Execution unverified |
| Lighthouse / Briscoe Wind | Named power counterparties | Delivery scope unverified |
| Siemens | Grace validation collaboration | No campus EPC award inferred |
The earlier Siemens collaboration concerns power behavior and validation associated with the Project Grace pilot. That history helps explain interest in controls, monitoring and commissioning. It does not identify Siemens as Dorothy’s general contractor or establish a full-campus equipment award. Likewise, Briscoe wind-operations relationships described in Soluna’s wind-farm explanation should remain attached to their generation roles.
Keep the capacity figures separate
The quarterly presentation separates the two campuses and their power positions. Dorothy’s 100 MW conditional Base Load classification covers existing campus interconnection capacity; Kati’s equivalent figure is 166 MW. Their combined 266 MW remains subject to ERCOT verification. Another 50 MW Dorothy request is under study. None of these figures establishes energized new AI capacity.
Dorothy 3’s broader campus envelope appears as up to 300 MW in the filing and 300-plus MW in current marketing. The first-phase 50 MW IT / approximately 75 MW gross plan is a separate scope. Briscoe Wind’s approximately 150 MW generation nameplate is another measure. Adding them would obscure the relationship between generation, grid access, building demand and computing load.
For a low-voltage estimator, these distinctions have practical consequences. A power announcement cannot establish rack counts, fiber quantities, security zones or controls points. Those quantities require an approved basis of design, construction documents and a defined tenant boundary. Keep assumptions visible in any preliminary estimate, including whether the work covers campus infrastructure, the base building or tenant equipment.
Where low-voltage work could develop
The completed fiber studies make outside-plant planning a specific area to investigate. Early construction also creates an opportunity to clarify underground pathways before later work restricts access. The categories below are LVN’s prospective trade analysis. No quantities, bid dates, package values or awarded installers were verified.
| Work area | Potential interface | Question for the buyer |
|---|---|---|
| Fiber / outside plant | Routes, ducts and entrances | Who owns design and testing? |
| Structured cabling | Pathways and tenant handoff | Where does each scope end? |
| Security | Access control and video | Who owns devices and networks? |
| Controls / monitoring | BMS, EPMS and SCADA links | Which protocols and points? |
| Life safety | Fire interfaces and coverage | What does the approved design require? |
| Commissioning | Tests and turnover records | Who witnesses acceptance? |
For fiber and pathways, request responsibility for trenching, duct placement, pull structures, building penetrations, seals and restoration. Clarify who supplies fiber, performs splicing, labels both ends and retains test records. Diverse routes need documented separation and coordinated entrances; a line on a conceptual illustration provides no assurance of physical diversity.
For controls and security, define network ownership before selecting equipment. Confirm switch ports, addressing, time synchronization, alarm routing and the handoff between operational technology and tenant systems. Commissioning should identify witnesses, expected results, exception handling and the party accepting turnover. These questions help prevent gaps between electrical, mechanical, network and specialty contractors without assuming any particular Dorothy architecture.
Kati 2 provides a useful comparison
Kati 2 is a separate Willacy County project developed with Metrobloks. The owner reports civil and earthworks there, construction-document progress, an onboarded but unnamed general contractor, long-lead orders and engineering for a substation expansion. Its November release identifies a new prospective tenant under a nonbinding 118 IT MW LOI after the earlier exclusivity period ended. A definitive lease and project financing remain milestones.
The Texas registration for Kati Building 1 lists 471,884 square feet, approximately 112 MW critical IT and an estimated $471.8 million cost. It identifies Soluna KK Energy Service Co LLC as owner and HKS as design firm. Those filed figures describe a registered building scope. The newer tenant LOI and the broader campus plan should retain their separate labels; no revised building quantity is inferred here.
Source wording also needs care. A syndicated release image caption places Dorothy in Willacy County; the filing and project materials identify Briscoe County. The presentation places Kati’s 118 MW LOI in a quarterly column, while the dated release says November. This report follows the dated release for timing and preserves the two counties. An exact signing day remains unverified.
Jobs, trades and preparation
In its prepared remarks, Soluna forecasts about 21 full-time Phase 1 jobs at Dorothy and about 40 at Kati once fully operational, with a preference for local workers and vendors. Those are owner forecasts for operating employment. LVN did not verify current vacancies, construction headcount or individual hiring commitments. No project-specific certification or prequalification list was established.
Technicians can prepare around portable skills: fiber inspection and cleaning, loss testing, splice documentation, labeling, grounding and bonding, pathway coordination and orderly turnover records. The Fiber Optic Association workforce resources provide general training context. OSHA Outreach training is a general safety resource. Neither link establishes a hiring requirement at these campuses.
A contractor capability package should identify comparable work, actual crew availability, testing equipment, insurance and the capacity to produce complete closeout records. Ask the confirmed procurement owner for its onboarding process and issued scope. Avoid staffing against a capacity headline or an operating-jobs forecast: package release, site access and acceptance responsibilities determine when a crew can productively mobilize.
What to watch next
The next useful evidence is a closed Dorothy joint venture, an executed tenant lease, confirmed project financing, a defined construction schedule and named procurement responsibilities. Public construction updates can then be compared with those commitments. For specialty firms, an issued package with a responsible buyer is the clearest basis for estimating and scheduling work.
Follow LVN Signal for source-linked construction intelligence and use the data-center map to place projects in context. Dorothy’s Silverton map reference is a city fallback, not a surveyed parcel or entrance. Keep that location limit in mind when planning route research or a site visit.
Join 35,000+ Low Voltage Pros
Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.