Dorothy 3A: A Conditional 50 MW AI Deal in Texas
AI & Data Centers

Dorothy 3A: A Conditional 50 MW AI Deal in Texas

August 26, 2026

Join Low Voltage Nation — Find project opportunities and showcase your company to thousands of industry professionals

Learn More →

Soluna and Applied Digital plan a 50 MW critical IT phase near Silverton. The venture, ChronoScale lease and Hypergate EPC remain conditional, with trade packages unverified.

Updated October 24, 2026, with the Dorothy 3A venture agreement and new company disclosures. This article retains the original Dorothy 3 development-watch URL.

Soluna’s proposed AI campus near Silverton, Texas, now has a defined initial phase and a prospective development partner. The company’s October 21 announcement describes a planned 50 MW critical IT facility with Applied Digital. ChronoScale has signed a nonbinding letter of intent to lease it. The venture closing and definitive project contracts remain conditional.

For low-voltage contractors, that creates a more specific project to evaluate. The useful questions are who will purchase each package, when design information becomes available, and which approvals move the work toward procurement. LVN has not verified an open specialty bid, a construction hiring campaign, a delivery date or energized Dorothy 3A capacity.

Dorothy 3A in context

The new phase sits within Dorothy 3, the development site in Briscoe County near Soluna’s earlier Dorothy facilities. Soluna’s August land announcement confirmed the purchase of 397 acres for a campus with potential capacity up to 300 MW. The adjacent Briscoe Wind Farm has a separate 150 MW generation nameplate. Those figures describe different assets and stages.

ItemReported scopeCurrent boundary
LocationBriscoe County, near SilvertonRural Texas development site
Dorothy 3A50 MW critical IT; about 75 MW grossPlanned initial phase
Dorothy 3 campusUp to 300 MW; 397 acresEarlier development envelope
Briscoe Wind150 MW generation nameplateSeparate power asset
Construction budgetUndisclosedFunding close unverified
Delivery and employmentUnverifiedNo confirmed jobs or opening date

The capacity distinction matters when comparing opportunities. Critical IT capacity describes the planned computing load; gross facility capacity uses a broader boundary. Wind nameplate measures a generating asset. None establishes an available low-voltage contract value. Estimating a package requires drawings, quantities, acceptance requirements and a defined division of work.

What the agreement establishes

Soluna’s October Form 8-K identifies Dorothy 3A as approximately 75 MW gross capacity and 50 MW critical IT. At closing, Applied affiliates would own 51% of the project company and Soluna affiliates 49%. The contemplated Applied cash subscription is $19,515,306, subject to credits for qualifying earlier development and equipment payments. The ground sublease carries $18,750,000 of attributed consideration.

These are transaction terms. A construction budget, committed construction financing and actual cash funding require separate evidence. The filing also reports that some site development has begun, without enough detail to establish vertical construction. It says the EPC and other ancillary contract forms were unfinished when filed.

That distinction guides the commercial response. A contractor can prepare a relevant capability package while keeping staffing and purchasing decisions tied to an actual solicitation. A signed venture agreement may help identify the future customer; the purchasing entity, contract terms and notice to proceed still determine whether a specific job can enter the backlog.

The companies and their qualified roles

The table separates the development parties, prospective tenant and named contractual counterparties. Website links establish company identity; the disclosure links establish their connection to this project.

CompanyProject connectionQualification
Soluna HoldingsSite developer; prospective 49% venture ownerClosing pending
Applied DigitalProspective 51% venture owner through affiliatesClosing pending
ChronoScaleProspective facility tenantNonbinding LOI
STX JV Holdings LLCDesignated project companyShared ownership transaction pending
Hypergate LLCContemplated EPC counterpartyDefinitive EPC unfinished
Lighthouse Electric CooperativePower-agreement counterpartyDelivery scope unverified
Briscoe Wind Farm LLCPower-agreement counterpartyDelivery confirmation required

The executed subscription agreement, section 1.3(h), names Hypergate LLC in a contemplated EPC closing deliverable. Section 1.3(p) calls for power-agreement confirmations from Lighthouse Electric Cooperative and Briscoe Wind. A verified Hypergate website and an executed EPC award have not been established. Lighthouse’s own website identifies the rural cooperative and its Briscoe County service footprint.

Earlier relationships also need their original scope preserved. Soluna’s Briscoe operating FAQ discusses CAMS and GE wind-maintenance responsibilities. Siemens’ Project Grace announcement describes technical validation with Soluna. Those sources provide power and operating context; Dorothy 3A construction awards require their own documentation.

Power and connectivity need separate proof

Soluna expects the initial phase to use both wind and grid supply, subject to definitive documentation. That is a development strategy. A contractor assessing schedule readiness should seek the actual delivery milestones, utility interface responsibilities and commissioning sequence. Nearby generation alone cannot establish when a data hall will accept load.

Connectivity has a similar evidence chain. Soluna’s June development update said Dorothy 3 fiber studies had started. A study creates a reason to examine carrier entrances and routes; carrier commitments, diverse physical paths and awarded outside-plant work require more detail. LVN has not verified a carrier list or fiber package for Dorothy 3A.

For an OSP team, useful diligence would cover route ownership, easements, utility crossings, demarcation points and who supplies duct, cable and restoration. For a facility integrator, it would cover the handoff between carrier facilities, building systems and tenant equipment. These are questions to bring to a documented procurement contact once that contact is identified.

Where low voltage could enter the work

The following scope categories are LVN’s assessment of potential data-center work. They are preparation areas, with quantities, specifications, installers and bid dates still unverified.

SystemPotential workEvidence needed
Fiber and OSPEntrances, pathways, splicing, testingCarrier routes and package boundaries
Structured cablingCopper/fiber support networks and labelsDesign, counts and acceptance criteria
Access control and CCTVPerimeter and building securitySecurity design and responsible buyer
Fire alarm interfacesMonitoring and life-safety integrationApproved design and trade boundaries
BMS and power monitoringControls networks, alarms and integrationPoint lists and sequences
CommissioningTesting, records and system handoffsAuthority and turnover requirements

A useful qualification package should demonstrate repeatable work: inspection records, organized test reports, clear labeling and examples of coordinated handoffs. For fiber contractors, document how crews handle cleaning, testing, failed results and retesting. For security or controls firms, show how changes are recorded and how responsibilities are divided with other trades. These are suggested preparation steps; the project’s eventual requirements will govern.

Separate construction installation from tenant equipment deployment when discussing scope. A facility developer, EPC, electrical contractor and tenant can purchase different portions of the same physical network. Ask who owns the specification, who accepts the work and who pays the invoice. A company’s appearance in a project announcement does not answer those three questions.

Pricing should follow that same discipline. A megawatt figure cannot supply a bill of materials for fiber, cameras, readers or control points. Route length, redundancy, density, equipment ownership and turnover requirements affect each package differently. With no verified construction budget or issued design, a dollar estimate for Dorothy 3A low-voltage work would be premature.

Jobs, trades and useful preparation

No project-specific construction headcount, permanent employment forecast or current vacancy was verified in the reviewed material. Treat Dorothy 3A as a development opportunity to monitor. Applicants should require a real employer, job location and requisition before treating general corporate hiring activity as a local opening.

For technicians building relevant experience, the Fiber Optic Association’s workforce resources offer a starting point for fiber training. BICSI provides ICT training and credential resources. These links are general preparation resources; LVN has not established a Dorothy 3A mandate for any particular credential.

Potentially relevant trades include fiber splicing and testing, pathway installation, structured cabling, electronic security, fire alarm integration and controls commissioning. Supervisors can prepare examples of daily quality checks, as-built updates and closeout documentation. Estimators can prepare questions about schedule access, material responsibility, testing witnesses and change-order handling. The aim is to be ready for a defined package when procurement information becomes public.

For site safety preparation, consult OSHA’s Outreach Training Program and confirm the eventual employer’s onboarding requirements. Course completion, manufacturer training and general data-center experience each address different needs. An individual credential should never be presented as automatic approval to work on this project.

The next milestones that matter

The transaction’s December 1 closing target allows specified extensions through December 31. These are transaction dates; facility delivery remains unverified. The agreement anticipates a county reinvestment-zone vote around November 9. LVN has not independently obtained the county agenda or verified an abatement award. The subscription agreement is the source for that anticipated milestone.

The most useful next evidence would be a closing announcement, definitive tenant lease, executed EPC agreement, county action and documented power-delivery milestones. For specialty firms, a public procurement route or named package buyer would make the opportunity more actionable. Later, issued design information and a solicitation could support estimating and workforce planning.

Each milestone answers a different question. County action addresses a public process. A lease addresses tenant commitment. An EPC agreement identifies delivery responsibility. A trade solicitation defines purchasable work. Following that sequence helps contractors allocate attention without assuming every announcement opens a bid window.

Follow the project through LVN Signal. Use the named parties, source documents and qualified scope to build a focused prospect list. The next useful step is identifying the confirmed buyer and requirements for the package your team can deliver.

Images are AI-generated concept illustrations. They do not depict verified Dorothy 3A architecture, site geometry or construction progress.

#project-spotlight·#ai-data-center·#data-center·#signal-content·#video-source·#silverton·#texas·#soluna·#applied-digital·#dorothy-3a·#planned