Westbourne Ashley Landing is a 285-unit mixed-use community under construction in Charleston, with five tracked low-voltage systems and a Q3 2028 completion target. LVN estimates $2.4M-$3.5M in cabling, security, AV, and intercom scope before owner-furnished equipment and services.
A $78.3 million mixed-use community now under construction in Charleston repeats five low-voltage systems across 285 apartments, shared amenities, retail frontage, and a precast parking garage. LVN estimates a $2.4 million to $3.5 million planning range for the structured cabling, access control, video surveillance, audiovisual, and intercom scope.
Project Overview
Westbourne Ashley Landing is the multifamily component of the larger Ashley Landing redevelopment in West Ashley. Charleston permit data describes a 285-unit mixed-use apartment building with leasing space, amenities, retail, an at-grade pool courtyard, and a precast garage. The Signal record carries a construction value of $78,331,071, lists the address as 1010 Conservation Place, and shows the permit issued on August 7, 2026. The same development is also identified in public project materials at the Ashley Landing site near Sam Rittenberg Boulevard and Old Towne Road.
Woodfield Development's project release says construction began in July 2026 and completion is anticipated in the third quarter of 2028. It describes studios through three-bedroom apartments, high-speed internet, garage parking with EV stations, package-concierge rooms, fitness and business spaces, a market, pet amenities, pickleball, and a saltwater pool. Those details turn a generic apartment permit into a repeatable technology program with residential, amenity, commercial, and parking zones.
The broader Ashley Landing plan will eventually include retail, restaurants, public gathering areas, pedestrian connections, and a central green. This spotlight prices only the $78.3 million multifamily permit represented by the selected Signal project. It does not add the value of the surrounding retail redevelopment, roads, townhomes, land, financing, or future tenant work.
| Project | Westbourne Ashley Landing |
| Location | 1010 Conservation Place / Ashley Landing, Charleston, South Carolina |
| Permit Value | $78,331,071 |
| Scale | 285 apartments with retail, amenities, pool courtyard, and precast garage |
| Status | Under construction; July 2026 start |
| Target Completion | Third quarter 2028 |
| LV Score | 9/10 |
| Primary Source | Charleston New Construction permits |
Key Players
The public team is unusually clear for a permit-led opportunity. Woodfield identifies the developer, builder, architect, civil/site consultant, and interior-design partners. The City of Charleston Technical Review Committee record separately identifies Ashley Landing Edens LLC as the property owner and SeamonWhiteside as the site-plan applicant. No electrical, structured-cabling, security, AV, or intercom award was found in the reviewed sources.
| Role | Company | Project Context |
|---|---|---|
| Developer | Woodfield Development | Developer of the 285-unit Westbourne residential component and the primary source for the current schedule and team. |
| General Contractor | Carter & Carter Construction | Lists Ashley Landing as an in-progress 285-unit project with a July 1, 2026 start. |
| Architect | Housing Studio | Architect named by both the developer and builder. |
| Site Design / Civil | SeamonWhiteside | Named development-team member and applicant in the city's site-plan review. |
| Property Owner / Master Developer | EDENS / Ashley Landing Edens LLC | Owner named in the city record and Woodfield's partner on the larger redevelopment. |
For low-voltage contractors, Carter & Carter is the most practical qualification door for subcontracted building systems, while Woodfield and EDENS may control portfolio standards, resident technology, and owner-direct services. Because construction is already underway, the near-term angle is not a generic introduction. It is a package-status check backed by multifamily production references, coordination drawings, testing samples, and a clear plan for phased turnover.
Low Voltage Systems Breakdown
Signal tracks five system lanes for the selected permit. The biggest challenge is repetition: hundreds of unit drops and devices must match shared risers, telecom rooms, security databases, amenity networks, and the turnover sequence. A small design inconsistency repeated 285 times becomes a material cost and schedule problem.
| System | Category | Likely Project Scope | Complexity |
|---|---|---|---|
| Structured Cabling | Data / Voice | Fiber and copper backbone, MDF/IDF buildout, apartment and leasing-office outlets, wireless-access-point cabling, security and intercom network support, amenity rooms, package areas, fitness and business spaces, garage coverage, labeling, certification, and digital closeout. | High |
| Access Control | Security | Resident and staff entries, garage and service access, amenity rooms, leasing and back-of-house spaces, equipment rooms, and pool or courtyard gates. The work must coordinate door hardware, life-safety release, credential policy, and phased occupancy. | High |
| CCTV / Video Surveillance | Security | Coverage planning for entrances, lobbies, package rooms, garage circulation, elevators, amenities, service areas, and the site perimeter. Storage, privacy, cybersecurity, analytics, and turnover of camera naming and views matter as much as device installation. | Medium-High |
| Audio/Visual | AV | Shared displays, presentation and collaboration points, fitness and resident-event audio, leasing-center systems, and possible digital signage. Retail-tenant AV should be separated from the base-building allowance unless the contract documents include it. | Medium |
| Intercom / Visitor Entry | Communications | Visitor call stations, resident directory and mobile-call workflows, controlled-entry release, service access, and integration with access control. The design must account for resident turnover, remote management, accessibility, and reliable network service. | High |
Fire alarm, emergency responder radio coverage, Wi-Fi electronics, parking controls, and smart-apartment devices may also affect pathways or coordination, but they are not among the five systems tracked on this Signal record. Contractors should ask who owns those interfaces instead of silently carrying them in a lump-sum allowance.
Estimated Low Voltage Value
Unit-count buildings are more reliable when modeled from repeatable device and cabling scope, then cross-checked against construction value. For Westbourne, a planning allowance of approximately $7,500 to $10,500 per apartment produces $2.1 million to $3.0 million for unit-facing and proportional backbone scope. Adding roughly $250,000 to $500,000 for shared amenity, leasing, retail-shell, courtyard, garage, and head-end work yields a rounded planning range of $2.4 million to $3.5 million.
| Apartment Count | 285 units |
| Residential Planning Allowance | $7,500 to $10,500 per unit |
| Residential / Proportional Backbone | $2.1 million to $3.0 million |
| Common, Retail-Shell, Garage, and Head-End Allowance | $250,000 to $500,000 |
| Estimated LV Planning Range | $2.4 million to $3.5 million |
| Planning Midpoint | Approximately $2.9 million |
The value cross-check lands in the same neighborhood. Three to four percent of the $78.3 million permit is about $2.35 million to $3.13 million; the upper end of the per-unit model reflects five coordinated systems plus a substantial amenity and garage program. This is an estimated planning range, not an awarded contract value or a claim that every system sits under one integrator.
Several owner-furnished boundaries can move the number. The estimate excludes carrier service and monthly broadband charges, resident-owned endpoint devices, retail-tenant technology beyond the base shell, leasing and property-management software, content subscriptions, EV charging power equipment, and decorative displays or fitness equipment bought directly by the owner. Smart locks, smart thermostats, managed Wi-Fi electronics, package lockers, and parking equipment should be priced only when the drawings, standards, and responsibility matrix assign them.
Skills and Certifications Required
Westbourne combines production installation with systems integration. The workforce needs crews that can move efficiently through repeated units without losing the documentation discipline required at telecom rooms, controlled doors, cameras, and networked head ends.
| System | Useful Certifications | Critical Skills |
|---|---|---|
| Structured Cabling | BICSI INST1, INSTC, INSTF; RCDD oversight | Pathway planning, copper and fiber termination, certification testing, rack buildout, labeling, unit templates, and as-builts |
| Access Control | Selected-platform factory training; ASIS PSP for senior design oversight | Door hardware, egress logic, credential databases, mobile access, phased turnover, and system integration |
| CCTV | VMS and camera-platform certifications; Network+ | PoE networks, camera placement, garage lighting coordination, storage calculations, privacy, and cybersecurity |
| Audio/Visual | AVIXA CTS, CTS-I, or CTS-D as role requires | Display and audio installation, DSP and control, AV-over-IP, commissioning, and end-user training |
| Intercom | Selected-platform manufacturer training | Directory management, call routing, mobile credentials, accessibility, door release, and turnover workflows |
Entry-level technicians can contribute to pathways, cable pulls, apartment rough-in, device mounting, and labels under a repeatable quality-control plan. Mid-level technicians should own terminations, certification, controller and camera commissioning, and punch-list closure. Senior leads need to coordinate risers, doors, networks, AV, visitor entry, life-safety interfaces, and owner standards across construction phases.
Contractors should verify South Carolina and Charleston licensing, registration, permit, and inspection requirements for their exact scopes. Security, fire alarm, communications, and door hardware can be divided differently among the electrical contractor, security integrator, owner vendors, and specialty subcontractors. The bid should name the credentialed party, interface owner, testing responsibility, and closeout deliverable for each lane.
Market Signal
Westbourne shows why multifamily work should not be dismissed as basic apartment cabling. The technology program extends from 285 residences into a garage, package rooms, leasing operations, fitness and business amenities, outdoor gathering space, retail frontage, and a visitor-access workflow. The best integrator is the team that standardizes the repeated unit while treating common spaces and head ends as a coordinated building platform.
The project is also part of a larger redevelopment, which creates account leverage beyond one permit. Woodfield says this is its 21st residential community in the Charleston region, while EDENS is guiding the broader Ashley Landing plan. A clean performance record here can support conversations about repeatable specifications, approved product stacks, warranty response, managed services, and future phases across two active development portfolios.
The selling motion should match the construction stage. Groundbreaking and financing are behind the project, and the GC lists the job as in progress. Contractors should ask which specialty packages are awarded, which remain open, and whether owner-direct systems need installation, commissioning, or change-order support. Useful proof includes multifamily unit-production rates, a sample riser and telecom-room closeout, camera and door schedules, commissioning forms, and references from phased occupied turnovers.
Bid Questions Worth Asking
- Which systems are held by Carter & Carter, the electrical contractor, Woodfield, or EDENS?
- Is there a Woodfield portfolio standard for managed Wi-Fi, access control, intercom, cameras, smart units, or package rooms?
- How many MDF/IDF rooms and fiber paths serve the apartments, garage, retail shell, and outdoor amenities?
- Are access control, visitor entry, mobile credentials, and elevator or garage access expected on one platform?
- What retail-tenant, parking, EV, fire-alarm, and public-safety-radio interfaces must the base-building systems support?
- How will apartment floors and shared amenities be released, tested, documented, and turned over through Q3 2028?
The core opportunity is not a speculative percentage attached to a large permit. It is a real, under-construction, 285-unit program with a named team, a defined schedule, five tracked system lanes, and enough repetition to reward contractors who bring disciplined production and closeout.
Find Projects Like This on Signal
LVN Signal tracks thousands of construction projects with low voltage opportunities across the country. Filter by city, system type, and project value to find your next bid.
Join 35,000+ Low Voltage Pros
Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.