$21.5M Young Junior High Renovation Starts With 5 LV Systems
Project Spotlights

$21.5M Young Junior High Renovation Starts With 5 LV Systems

November 24, 2026

Join Low Voltage Nation — Find project opportunities and showcase your company to thousands of industry professionals

Learn More →

Arlington ISD is moving a $21.5 million addition and renovation at Young Junior High into construction with a fire alarm replacement, expanded camera coverage, access/security upgrades and district communications work. The modeled low-voltage construction opportunity is approximately $989,000, with a practical range of $860,000 to $1.24 million.

A $21.5 million addition and renovation at Young Junior High in Arlington, Texas is entering its main construction window with five low-voltage work lanes: Fire Alarm, Access Control, CCTV, Structured Cabling and integrated Security. Using a K-12 construction benchmark and a five-system coordination factor, the modeled low-voltage construction value is approximately $989,000, with a practical planning range of $860,000 to $1.24 million.

Project Overview

The project at 3200 Woodside Drive is the Phase 4 modernization of an occupied Arlington Independent School District campus. The Texas Department of Licensing and Regulation filing identifies a 154,570-square-foot public project with elevator and north gym entry additions, enclosure of the central courtyard, a new fire-suppression system, replacement of the fire-alarm system, HVAC replacement and interior renovations. The filing carries a $21.5 million estimated construction cost, a scheduled start date of November 23, 2026, and an August 1, 2027 completion date.

City permit data adds an important scope distinction. Arlington issued the building permit on October 26 for a 19,470-square-foot addition and remodel with MEP work and a phased occupancy plan. The 19,470 square feet describes the addition/remodel permit scope, while the TDLR area describes the broader existing campus affected by the program. Contractors should keep those two measures separate when estimating pathways, device counts and occupied-building labor.

The Arlington ISD 2019 Bond project page says paving work began during the summer and places the main renovation program between summer 2026 and fall 2027. Trade-project tracking lists the job as post-bid after an October 7 bid date. That means this is no longer an open prime-bid story. The near-term business-development angle is the awarded prime, second-tier specialty packages, approved-vendor channels, addenda, substitutions, commissioning and change work as mobilization turns into active construction.

ProjectYoung Junior High Addition and Renovation, 2019 Bond Phase 4
Location3200 Woodside Drive, Arlington, Texas 76016
Construction Value$21.5 million
Program Area154,570 square feet in the TDLR filing
Addition / Remodel Scope19,470 square feet in the city permit description
ScheduleNovember 23, 2026 to August 1, 2027 in the TDLR filing
StageReview complete; post-bid; construction mobilization
LV Score10/10

Key Players

The owner and design firm are source-backed. The public district page still labels the construction manager as TBA, and the city permit record does not publish the building contractor. LV firms should not guess at the prime. The productive move is to monitor Arlington ISD award records and the project document trail, then approach the awarded builder or electrical prime with a scope-specific qualification package.

RoleOrganizationWhy It Matters
OwnerArlington Independent School DistrictPublic owner, 2019 Bond program sponsor and standards authority for district security, communications and device access.
ArchitectLBL ArchitectsTDLR design firm of record. The Arlington-based firm specializes in institutional and government work, including K-12 renovation.
Construction Manager / GCNot publicly named in the reviewed official recordsThe district project page shows TBA. Verify the award before sending pricing or claiming a project relationship.

Low Voltage Systems Breakdown

This is an occupied-school modernization, not a clean-sheet technology build. Existing pathways, legacy devices, active bell schedules, after-hours access and phased turnover will influence labor as much as hardware quantities. The district's published scope confirms camera, key-system, communications and device-access upgrades; the TDLR filing explicitly confirms a full fire-alarm replacement.

SystemCategoryProject-Specific ScopeComplexity
Fire AlarmLife SafetyReplacement across a renovated campus, coordinated with new fire suppression, HVAC shutdowns, phased occupancy and final acceptance. The integrator must plan migration and testing without leaving occupied areas unprotected.High
Access ControlSecurityDoor hardware, credentialed access and key-system coordination at renovated entries, the new north gym entrance and altered interior circulation. Existing district standards will drive controller, reader and credential compatibility.High
CCTV / Video SurveillanceSecurityExpanded camera coverage and upgraded camera software are part of the district's campus scope. Renovated corridors, enclosed courtyard edges and new entrances create changed views that require field validation rather than a simple device-for-device swap.Medium-High
Structured CablingData / VoiceBackbone and horizontal cabling to support district communications, security endpoints and device upgrades in renovated areas. Reuse decisions should be based on test results, pathway capacity and current district standards.Medium-High
Integrated SecurityCoordinationA coordination lane connecting cameras, access, key systems, district communication and emergency procedures. This line should not be priced as five more devices; it represents software, programming, interfaces, testing and turnover across the named security systems.High

Estimated Low Voltage Value

For a comprehensive K-12 renovation, a 4% low-voltage benchmark applied to the $21.5 million construction value produces an $860,000 base. Five coordinated systems increase field coordination, programming, testing and closeout effort; applying the skill model's 1.15 multiplier produces approximately $989,000. An upper cross-check at 5% with the same multiplier reaches about $1.24 million.

Construction Value$21,500,000
K-12 Base Benchmark4% of construction value
Five-System Multiplier1.15x
Modeled LV Value$989,000
Practical Planning Range$860,000 to $1,240,000

The range is more useful than a false single-number promise. Fire-alarm replacement and occupied-school phasing can push labor upward, while district-furnished equipment can move hardware value out of the trade contract. A strong proposal separates rough-in, pathways, cable, devices, programming, demolition, temporary protection, testing and after-hours work so the owner can see where alternates change cost.

This estimate excludes fire-sprinkler pipe, pumps and suppression hardware; HVAC equipment and mechanical controls not assigned to the LV contractor; student and staff endpoint devices; network servers; camera-software enterprise licensing; cloud subscriptions; classroom audiovisual equipment; furniture and other owner-furnished technology unless the contract documents explicitly place those items in the package. Those exclusions matter because Arlington ISD's broader bond program includes district-wide security cameras, network servers and technology replacements that should not automatically be charged to this single building permit.

Where the Opportunity Sits Now

The prime bid date has passed, but the project is entering the stage when detailed coordination becomes real. Fire-alarm matrix review, pathway conflicts, reader-door schedules, camera fields of view, interface responsibilities and shutdown sequencing are usually resolved through submittals and coordination meetings. Specialty firms with a documented Texas license position, K-12 references and the ability to work around an occupied campus can still create leverage with the awarded construction team.

The outreach package should be specific: identify which of the five lanes the firm self-performs, list compatible manufacturers without pretending a basis-of-design has been confirmed, show available NICET and BICSI personnel, and state after-hours testing capacity. Ask for the current electrical and technology bid tabs, accepted alternates, responsibility matrix and addenda. A generic “we do low voltage” email will disappear; a one-page migration and commissioning plan is more likely to reach the estimator or project manager who owns the risk.

Skills and Certifications Required

SystemUseful CredentialsCritical Skills
Fire AlarmTexas fire-alarm license appropriate to the work; NICET Fire Alarm Level II or higher for lead rolesNFPA 72, replacement phasing, SLC/NAC work, HVAC interfaces, testing and AHJ coordination
Structured CablingBICSI INSTC / INSTF; RCDD oversight for design questionsCopper and fiber testing, pathway planning, labeling, occupied-campus cutovers and closeout records
Access ControlManufacturer training; PSP useful for senior security leadershipDoor hardware, reader/controller wiring, credential migration, network coordination and life-safety release logic
CCTVVMS and camera-manufacturer certification; Network+ useful for techniciansPoE, camera placement, field-of-view validation, storage calculations and district software integration
Security IntegrationRCDD, PSP or equivalent integration experienceResponsibility matrices, API/interface planning, commissioning scripts, training and as-built documentation

Texas regulates fire-alarm companies and individual license holders through the State Fire Marshal's Office. Firms pursuing the replacement should confirm their registration and staffing against the current Texas Department of Insurance licensing guidance. Entry-level technicians can support cable installation, device mounting and labeling under proper supervision; senior technicians should own migration planning, programming, integrated testing and turnover.

Market Signal

Young Junior High is a useful North Texas signal because the work combines building-condition upgrades with security and life-safety modernization. The district is not treating cameras, access, communications and fire alarm as isolated purchases. They ride alongside courtyard enclosure, new entries, HVAC replacement and interior renovation, which means the winning LV team must coordinate with architectural, mechanical, electrical and door-hardware schedules.

It is also a repeat-account signal. Arlington ISD's 2019 Bond Phase 4 includes multiple campus renovations and district technology investments. Contractors who deliver clean submittals, predictable shutdowns, accurate test records and staff training at one occupied campus build evidence for the next one. The account leverage is not a one-off device sale; it is becoming a dependable participant in a standards-driven public-school program.

The immediate lesson is timing. Public bid boards may show “post-bid,” yet the LV risk is only beginning to move from drawings into field conditions. Firms that track permits, accessibility filings, bond pages and award records together can approach the right contract holder with a scoped solution before coordination gaps become change orders.

Find Projects Like This on Signal

LVN Signal tracks thousands of construction projects with low voltage opportunities across the country. Filter by city, system type and project value to find your next bid.

Browse Signal Projects

#project-spotlight·#arlington·#texas·#school·#signal-content·#video-source

Join 35,000+ Low Voltage Pros

Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.

Back to Home