Low Voltage Nation
SignalJobsCompaniesProsFeed
Project Jupiter Tops Out as Power Review Continues
AI & Data Centers

Project Jupiter Tops Out as Power Review Continues

June 21, 2026

Join Low Voltage Nation — Find project opportunities and showcase your company to thousands of industry professionals

Learn More →

Jupiter’s first 855,000-square-foot portion has topped out. Clayco and Kiewit are named; proposed power limits, permit review and specialty awards remain separate milestones.

Updated October 28, 2026. Project Jupiter has reached a visible construction milestone in southern New Mexico. In its October 22 announcement, Clayco said the first 855,000-square-foot portion had topped out. Clayco and Kiewit New Mexico Co. are the general-contractor joint venture for that portion, selected by Oracle and STACK Infrastructure in August 2025. Groundbreaking followed in October 2025.

For low-voltage contractors, the useful question is what comes after the structural frame: released trade packages, site access, coordinated pathways, equipment interfaces and acceptance testing. Those details determine whether a large campus becomes an actionable opportunity. This update identifies the named organizations and separates verified construction progress from proposed power capacity, employment forecasts and unresolved specialty awards.

Project snapshot

ItemCurrent evidenceQualification
LocationSanta Teresa / Doña Ana County, NMCampus and adjacent microgrid
Structural milestone855,000-square-foot first portionTopped out; commissioning unverified
Power design2,462 MW generation nameplateApplicant proposal
Operating limit1,600 MW requested capFinal permit unverified
Critical IT / energized ITUndisclosed / unverifiedNo inferred capacity
Air-permit hearingDecember 7, 2026 scheduledFuture proceeding
Specialty packagesElectrical, fiber and controlsBuyers and awards unverified

A structural topping-out announcement establishes a specific stage of building work. It does not answer whether mechanical and electrical systems are complete, how much equipment is commissioned, or when customer computing loads can operate. Treat each of those as a separate delivery milestone when planning labor, material commitments and testing resources.

Two power numbers with different meanings

The October 22 administrative supplement contains an October 14 response prepared by Trinity Consultants for Yucca Growth Infrastructure and Bloom Energy. It describes 2,462 MW of generation nameplate and requests a permit condition limiting operating output to 1,600 MW. The distinction appears explicitly on PDF page 3. The requested cap belongs to the applicant's proposal; an issued permit establishing that condition was not verified.

Neither number establishes critical IT load. A power system's installed equipment rating, its allowed output and the capacity available for computing describe different things. Without the relevant electrical design, operating conditions and commissioning evidence, converting one into another would create false precision.

Oracle's October 15 announcement describes the revision as reducing projected emissions by approximately 35% while leaving planned IT capacity unchanged. It supplies no numeric IT rating. Its emissions language concerns modeled performance and a pending application, rather than measurements from an operating campus. The company's headline uses the word “permitted,” but the same release describes the operating condition as proposed.

The April 27 Oracle announcement provides the earlier design context: BorderPlex Digital Assets and Bloom Energy were named, with up to 2.45 GW of installed fuel cells proposed. That historical figure should remain attached to its date. The newer administrative filing supplies the more precise nameplate and operating-cap figures used here.

Construction and the air case have separate milestones

Oracle's September 14 construction statement says the data-center buildings and proposed microgrid occupy separate, adjacent sites and have separate operators. It presents the company's position on which activities fall under the air-permit process. That statement helps explain the project's organization; it is not an independent finding that every disputed activity complies with all permit requirements.

The October 16 amended scheduling order sets the public hearing for December 7, with technical testimony due November 17. A separate notice on discovery motions schedules a hearing for October 29. As of this update, both hearing dates are future events. A hearing notice establishes a scheduled proceeding, not its result.

The NMED docket identifies the matter as AQB 26-57(P), concerning application NSR 10883. The obtained document list extends through an October 26 applicant filing. A final air permit and a written disposition resolving the latest dismissal motions were not verified for this article. Contractors should ask for the applicable issued approvals and release conditions before relying on an assumed power-start date.

Named companies and their documented roles

OrganizationDocumented roleEvidence
OracleAI/cloud operatorOperator announcement
STACK InfrastructureCampus developerConstruction announcement
BorderPlex Digital AssetsDevelopment partnerApril announcement
ClaycoGC joint-venture memberFirst-portion milestone
Kiewit New Mexico Co.GC joint-venture memberFirst-portion milestone
Bloom EnergyFuel-cell vendorApplication supplement
Yucca Growth InfrastructureMicrogrid applicant/developerOfficial hearing notice
Trinity ConsultantsAir permitting and modelingConsultant response

The subsidiary name matters: the announcement identifies Kiewit New Mexico Co. The evidence does not assign every Kiewit business a campus role. Similarly, Trinity's work in the obtained material concerns environmental permitting and modeling; it does not establish a data-hall design or low-voltage engineering award.

No electrical, structured-cabling, outside-plant fiber, security, controls, fire-alarm or commissioning package award was established in the reviewed sources. A named general contractor is a useful starting point for procurement research. It does not establish that a bid window is open, that a subcontract remains available or that any particular integrator is already selected.

Where low voltage could enter the delivery program

The following scopes are LVN's trade analysis. They identify practical questions to ask when drawings and procurement information become available. They do not describe awarded work, verified quantities or a confirmed project specification.

SystemPotential workConfirm before bidding
Fiber / outside plantEntrances, pathways, splicing and testsRoutes, buyer and release dates
Structured cablingSupport networks and documentationMedia types and test limits
Pathways / bondingTray, supports and coordinationTrade boundaries and details
Access control / CCTVPerimeter and building systemsApproved design and integrator
Controls / OT networksPower and cooling interfacesArchitecture and ownership
Fire-alarm interfacesMonitoring and integrated testingApproved sequence and authority
CommissioningTest records and turnoverAcceptance criteria and lead

For a fiber contractor, start with the physical route and the party that controls it. Ask where the carrier demarcation sits, who owns the entrance duct bank, when trenches or pathways become accessible, and which team accepts the installed links. Route diversity must be demonstrated in design documents; two cables do not automatically mean two independent routes.

For cabling and pathway teams, a useful bid package needs boundaries between civil, electrical and communications work. Confirm responsibility for sleeves, supports, firestopping, grounding and bonding, identification and closeout records. A large floor area alone cannot produce a defensible cable count or labor estimate. Released layouts and acceptance requirements provide that basis.

Security and controls contractors should look for clear ownership of network interfaces. Access systems, video, building controls and power monitoring may involve different designers and operators. Before proposing equipment, ask who approves the architecture, manages addressing and credentials, witnesses integration tests and accepts maintenance documentation. Those are questions for the eventual project team, rather than assumptions about Jupiter's systems.

Testing capacity deserves early attention. Installation crews, test technicians and commissioning personnel may need different work windows and access permissions. A contractor can prepare by showing how it tracks deficiencies, preserves test results and produces an auditable handover. The reviewed sources do not identify Jupiter's commissioning lead, required instruments or final acceptance procedures.

Jobs, trades and preparation

The contractor announcement forecasts 7,000 construction jobs and more than 3,100 ongoing project-supported roles. The official project website gives a different ongoing-jobs figure of 1,500. The available material does not reconcile the definitions, time periods or direct-versus-supported employment assumptions. Neither estimate is a count of verified vacancies or people currently working at the site.

For technicians, the useful preparation is specific and demonstrable: fiber inspection and cleaning, splicing and loss testing, pathway installation, labeling, grounding and bonding, and organized test records. For leads and supervisors, add drawing review, coordination with electrical and civil crews, punch-list management and clear daily documentation. These are transferable capabilities; project-specific requirements still need confirmation.

The Fiber Optic Association's workforce resources provide a starting point for fiber training. BICSI provides ICT education and credential information, and OSHA's construction resources cover general safety topics. Consult each employer for the credentials, site induction, lift access and task qualifications it actually requires. Listing a resource here does not mean Jupiter mandates that credential or has opened a recruitment program.

Investment and schedule need their qualifiers

The Doña Ana County project page describes an estimated investment of up to $165 billion. That ceiling does not establish a funded construction budget, an executed financing close or the value of low-voltage contracts. Applying an arbitrary percentage to the headline number would produce a speculative trade-market estimate, so none is presented here.

The county's updates page retains anticipated initial operations in Q4 2026 and phase-one completion in Q3 2028. Those are published targets. This review did not establish that power delivery, permitting or commissioning can support them. There is no verified day-specific completion date to use for staffing commitments.

Location also has a limit. The official microgrid notice supplies a point at 31.8183, -106.6792. It identifies the associated power facility near the campus, not the topped-out building's surveyed centroid or a construction entrance. Suppliers and visiting contractors should obtain the authorized delivery address and access instructions directly from the contracting team.

What would make the next update actionable?

The strongest next evidence would be an issued air-permit decision and its conditions, documented fuel and power readiness, a dated commissioning milestone, or a specialty award that names the buyer and scope. For procurement, ask for a released package, bidding instructions and an accountable contact. For employment, look for a current vacancy tied to this facility and a named employer.

Until then, Jupiter offers a verified structural milestone and a clearer organization map, with material delivery questions still open. Use LVN Signal to follow AI/data-center construction opportunities, compare named project teams and identify source-backed changes worth investigating. Bring the project evidence into the conversation before committing a crew or pricing an assumed scope.

Illustrations are AI-generated concepts, not photographs or approved renderings of Project Jupiter. Reporting distinguishes source statements, applicant proposals and LVN's prospective trade analysis.

#project-spotlight·#ai-data-center·#data-center·#signal-content·#video-source·#santa-teresa·#new-mexico·#oracle·#clayco·#kiewit·#under-construction

Join 35,000+ Low Voltage Pros

Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.

Back to HomeView Original Post