Harris County structured cabling follows Texas state exemptions. Low voltage communication circuits generally exempt. Verify jurisdiction—Houston has different requirements.

Structured Cabling Permit Requirements in Harris County, Texas

Quick Answer: Structured cabling and data network installations in unincorporated Harris County generally follow Texas state exemptions for low voltage work. Class 2, Class 3, and communication circuits are exempt from state electrical licensing requirements. However, commercial projects may require building permits for associated work, and projects within Houston city limits have different requirements.

Understanding Harris County Jurisdiction

Harris County permit requirements apply to unincorporated areas—areas outside the 34 incorporated cities within the county.

  • Unincorporated Harris County – Follow this guide
  • City of Houston – See our Houston Structured Cabling Permit Guide
  • Other cities (Katy, Spring, Pasadena, Humble, Cypress, Baytown, Tomball, Kingwood, La Porte, etc.) – Contact that city's permit office

When Is a Permit Required?

Harris County follows Texas state exemptions with some important considerations:

State-Level Exemptions

Per the Texas Department of Licensing and Regulation (TDLR), the following are exempt from state electrical licensing requirements:

  • Class 1, Class 2, and Class 3 remote control, signaling, or power-limited circuits
  • Communications circuits (voice, data, network cabling)
  • Optical fiber cable installations
  • Associated raceways as defined by the National Electrical Code

This means most structured cabling work—Cat5e, Cat6, Cat6A, and fiber optic installations—does not require state electrical licensing in Texas.

Municipal Override Authority

Under Section 1305.201 of the Texas Electrical Safety and Licensing Act, municipalities can impose additional requirements beyond state exemptions. While unincorporated Harris County generally follows state exemptions, specific projects may require permits for:

  • Structural modifications (wall penetrations, ceiling work)
  • Work requiring 120V connections (network equipment power)
  • Projects in commercial buildings with specific permit requirements
  • Fire-rated wall penetrations requiring firestopping inspection

When to Verify Requirements

Contact Harris County Permits office through the ePermits Portal for projects involving:

  • Large commercial installations
  • Data center infrastructure
  • Work in critical facilities
  • Projects requiring inspection documentation

Contractor Requirements

Even without permit requirements, there are important contractor considerations:

State-Level Status

Texas does not require a state license specifically for structured cabling installation when work is limited to:

  • Class 2/3 circuits
  • Communications circuits
  • Optical fiber

However, work must still comply with NEC Chapter 8 requirements.

For comprehensive information on Texas low voltage contractor licensing, see our Texas Low Voltage License Guide.

Industry Certifications (Recommended)

While not legally required, these certifications demonstrate competency and may be required by commercial clients:

  • BICSI Installer (Copper or Fiber)
  • BICSI Technician
  • BICSI RCDD (for design work)
  • Manufacturer certifications (CommScope, Panduit, Corning, etc.)

When Electrical Licensing Applies

If your structured cabling project includes 120V work (installing outlets for network equipment, UPS systems, etc.), that portion requires electrical licensing and permits.

Application Process

For Standard Low Voltage Work

Most structured cabling installations in unincorporated Harris County proceed without permits:

  1. Verify project scope – Confirm work is limited to low voltage communication circuits
  2. Confirm jurisdiction – Verify project is in unincorporated Harris County, not within city limits
  3. Coordinate with building management – Obtain access and any property-specific requirements
  4. Install per code – Follow NEC Chapter 8 and TIA/EIA standards
  5. Test and certify – Provide test results and as-built documentation

For Projects Requiring Permits

If permits are needed, submit through the Harris County ePermits Portal.

Contact Information

Department Contact Purpose
HC ePermits Portal epermits.harriscountytx.gov Online permit applications
HC Engineering - Permits oce.harriscountytx.gov Permit information
Texas TDLR (512) 463-6599 State licensing info

Fees and Timeline

Standard Low Voltage Work

Item Cost Notes
Permit Fee $0 Exempt work requires no permit
Inspection Fee $0 No county inspection for exempt work

When Permits Are Required

Permit Type Timeline Notes
Electrical Permit Varies For 120V work only
Building Permit Varies Structural modifications

Residential vs. Commercial Projects

Residential Structured Cabling

  • No permit required for low voltage data/voice cabling
  • Homeowner self-installation permitted
  • Professional installation recommended for warranty coverage
  • Follow NEC Chapter 8 for compliant installation

Commercial Structured Cabling

  • Generally no permit required for standalone cabling work
  • Building management may require contractor documentation
  • Testing and certification typically contractually required
  • TIA/EIA standards compliance expected
  • Fire-rated wall penetrations require proper firestopping

Code Compliance Requirements

NEC Chapter 8

All structured cabling must comply with NEC Chapter 8 (Communications Systems):

  • Proper cable ratings (CM, CMR, CMP) for installation location
  • Plenum-rated cable required in air handling spaces
  • Riser-rated cable for vertical runs between floors
  • Separation from power conductors per NEC requirements
  • Proper support and routing

Bonding and Grounding

Per NEC Article 250 and Chapter 8:

  • Telecommunications bonding backbone required
  • Equipment racks must be properly bonded
  • Fiber optic cable with metallic components requires grounding
  • Primary protectors required for outside plant cables

Firestopping

When penetrating fire-rated walls or floors:

  • Appropriate firestop material required
  • Must maintain original fire rating
  • Documentation may be required
  • This requirement applies regardless of permit status

TIA/EIA Standards

  • TIA-568 – Commercial Building Telecommunications Cabling Standard
  • TIA-569 – Telecommunications Pathways and Spaces
  • TIA-606 – Administration Standard for Telecommunications Infrastructure
  • TIA-607 – Telecommunications Bonding and Grounding

Pro Tips from the Field

Verify Jurisdiction: Harris County is large with 34 incorporated cities. Always confirm whether your project is in unincorporated Harris County or within city limits before quoting.

Document Everything: Even without permits, maintain thorough documentation. Test results, as-built drawings, and cable labeling protect you legally and help with future service.

Know Your Firestopping: Fire-rated penetrations are a common point of inspection issues. Use proper firestop materials and document your work.

Get BICSI Certified: While not legally required, certifications open doors to larger commercial contracts. Many Houston-area enterprises specify certified installers.

Test Everything: Always test and certify installations. Professional test results demonstrate quality and catch problems before they become service calls.

Future-Proof: When quoting jobs, recommend Cat6A over Cat6. The labor cost is the same, and customers appreciate forward-thinking recommendations.

Stay Ahead of Project Activity

Want to know when structured cabling projects hit permits in Harris County before they reach bid boards?

LVN Signal monitors permit activity across Texas and alerts you to opportunities the moment they're filed.

→ Explore LVN Signal

Related Guides

Last updated: January 2026. Information is subject to change. Always verify current requirements with Harris County before beginning work.

Tags

#permits
#texas
#structured-cabling
#licensing
#harris-county

Join 35,000+ Low Voltage Pros

Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.