Join Low Voltage Nation — Find project opportunities and showcase your company to thousands of industry professionals
HITT leads Helios I Phase II construction toward first halls in Q2 2027. Closed financing, contracted capacity and prospective low-voltage scopes have distinct boundaries.
Galaxy’s Helios campus in Afton, Texas, has a defined next construction phase: two buildings and a supporting substation, a named general contractor, and financing that closed in July. In its October 27 update, Galaxy said Helios I, Phase II construction was progressing toward first data-hall deliveries in the second quarter of 2027. The operator described work as on schedule and within budget. Those are management assessments and delivery targets, rather than independently verified completion milestones.
For low-voltage contractors, the useful question is which organization controls each package as the new halls move toward fit-out and turnover. HITT is the documented Phase II general contractor. Electrical, fiber, security, controls and commissioning package awards remain unverified in the reviewed sources. The project offers a reason to investigate procurement, while the public evidence still leaves the specialty contracting chain open.
Project snapshot: separate the capacity measures
| Scope | Reported measure | Qualification |
|---|---|---|
| Location | Afton, Dickens County, Texas | West Texas campus |
| Helios I, Phase I | 133 MW IT / 200 MW gross | Operator reports delivery |
| Helios I, Phase II | 260 MW critical IT | Under construction |
| CoreWeave’s three phases | 526 MW IT / 800 MW gross | Contracted total |
| Separate Helios II | 830 MW gross power | Unleased expansion |
| First Phase II halls | Q2 2027 | Operator target |
The August 5 results provide the capacity definitions and identify HITT’s appointment. They distinguish Phase II’s 260 MW of critical IT from the 526 MW contracted across CoreWeave’s three Helios I phases. Gross power includes a different electrical boundary from critical IT. Neither contracted totals nor approved expansion power establishes how much computing load is energized today.
Galaxy’s August 12 construction update described eight Phase II halls, with the first expected in Q2 2027, seven by year-end, and the last in early 2028. That sequence helps explain why a single campus completion date would be misleading. A phased handover can create several distinct documentation, testing and acceptance events. Contractors should establish which hall, system and delivery package an inquiry concerns before committing labor or quoting a schedule.
Named companies and their documented roles
| Organization | Documented role | Evidence |
|---|---|---|
| Galaxy Digital | Campus operator | October update |
| Galaxy Helios II LLC | Registered building owner | Texas filing |
| CoreWeave | Helios I tenant | Contracted capacity |
| HITT Contracting | Phase II general contractor | Construction update |
| Stantec Architecture | Registered design firm | Texas filing |
| Clayco | Initial 133 MW conversion | Contractor project page |
| Total Safety | Campus emergency services | August agreement |
Phase boundaries matter when evaluating experience and approaching a project team. Clayco’s own project page describes the initial 133 MW liquid-cooled conversion. It supports that specific role; the later Phase II appointment belongs to HITT. Stantec Architecture appears as the design firm in the Texas registrations. The records reviewed here do not establish a separate named engineering appointment or identify the specialty installation firms.
The Total Safety agreement covers fire, rescue, paramedic and EMT services at the campus. It creates a documented emergency-response relationship, but does not identify the fire-alarm installer, the controls integrator or the party performing integrated systems testing. A contractor reviewing the opportunity should keep those responsibilities distinct. Current emergency-service staffing and individual vacancies were not independently verified.
Closed financing and filed estimates cover different scopes
Galaxy’s second-quarter Form 10-Q, PDF page 52, reports that its financing subsidiary closed $3.507 billion principal of senior secured notes on July 28. The notes carry a 9.875% coupon and mature August 1, 2031. The filing associates the financing with two Helios buildings. This is a completed July financing event, rechecked for this report, rather than a new October capital raise. Note principal is also different from net proceeds or verified total campus construction cost.
Texas architectural-barriers records describe a three-building grouping. Helios 2 lists 199,124 square feet and a $900 million estimated cost; Helios 3 and Helios 4 each list 349,594 square feet and $1.3 billion. Together, the registrations total 898,312 square feet and $3.5 billion in estimates. They give completion dates of February 8, August 29 and November 29, 2027, respectively.
Those registrations use 1003 FM 193, Galaxy Helios II LLC and Stantec Architecture. Their building labels, the owner’s legal name, Helios I’s commercial Phase II, and the separate expansion called Helios II do not establish an exact mapping between the three registrations and the two financed buildings. Consequently, the filed cost total should remain attached to its registration group. Applying a generic low-voltage percentage to that total would produce a dollar figure with an unresolved scope.
The filings’ “Review Complete” status concerns architectural-barriers review. It does not establish a complete set of building, environmental, water, generation or energization approvals. Registered completion dates are estimates within those records. A prospective subcontractor still needs the applicable issued drawings, contract schedule and released work area to evaluate an actual package.
Power and permitting remain separate delivery questions
Galaxy’s September power-process disclosure distinguishes earlier Helios power approvals from conditional Batch Zero classifications and additional studied requests. The 1,000 MW Helios III request belongs to that longer-term pipeline. Conditional classifications carry audit and verification qualifications; they do not independently demonstrate energized IT capacity.
In the October 27 investor-call transcript, management discussed the separate Helios II expansion, prospective tenants and an earliest expected energization around mid-2028. It also described construction permits as obtained while certain diesel-backup and potable-water approvals remained outstanding. These are operator statements; an independent, complete permit inventory was not obtained for this report. The transcript warns that transcription errors are possible.
For trade planning, that leaves several milestones to check independently: availability of the work area, electrical readiness, commissioning access and the owner’s acceptance process. A forecast first-hall date can guide an initial conversation. It cannot replace the package-level sequence or resolve the dependencies between the hall and its supporting infrastructure.
Where low voltage could enter the construction sequence
The following scopes are LVN’s analysis of potential work around new data halls and supporting infrastructure. The reviewed sources establish no awarded specialty package, open tender, bill of materials or released quantity for these systems.
| System | Potential work | Evidence needed |
|---|---|---|
| Fiber / outside plant | Routes, splicing, testing | Route plans and buyer |
| Structured cabling | Support networks and labels | Issued specifications |
| Pathways / bonding | Tray and grounding interfaces | Trade responsibility matrix |
| Access / CCTV | Building and perimeter links | Security design and award |
| Controls / OT | Power and cooling interfaces | Approved network architecture |
| Fire-alarm interfaces | Monitoring and integration | Approved sequence and installer |
| Commissioning | Acceptance and turnover records | Test plan and lead |
Preparation should start with responsibility boundaries. Ask who buys the cable and pathway package, who owns the network design, and who accepts the test results. Confirm whether outside-plant work and indoor cabling are separate procurements. Establish the handoff between electrical power, controls networks and security systems. These questions turn a broad campus lead into a scope that can be estimated and staffed.
Documentation deserves attention before installation begins. A useful readiness package could include sample labeling schedules, fiber inspection and test records, equipment calibration information, as-built deliverables and a commissioning issue log. These are suggested preparation materials, not published Helios contract requirements. The appointed buyer must confirm the actual formats, acceptance thresholds, warranty conditions and subcontractor qualifications.
Jobs, trades and skills: prepare without inventing vacancies
No source-backed construction headcount, permanent employment total or current vacancy was established in the reviewed materials. The named firms offer starting points for researching legitimate opportunities, but a company’s presence in this report is not a hiring announcement. Confirm employer, location, phase, start date and travel terms against a current requisition before treating a role as available.
Fiber technicians can use the Fiber Optic Association’s workforce resources as general preparation. Relevant subjects include handling, inspection, cleaning, splicing, testing and records. BICSI provides an ICT training and credential reference. Neither resource establishes a required Helios certification. Applicants and employers should match training to the actual package and its documented acceptance criteria.
For installers and supervisors, OSHA’s construction resources are a general safety reference. Verify the employer’s site orientation, equipment authorization and task-specific requirements. Controls and commissioning staff should be prepared to discuss interface documentation, change control, test evidence and turnover. Travel crews should obtain verified site access instructions: the currently available map point resolves to Afton town center and is unsuitable as a building entrance or delivery destination.
What to watch next
The most useful next disclosures would identify Phase II specialty buyers and awards, clarify the building-to-registration mapping, and document the first hall’s testing and acceptance sequence. Future operator updates can show whether the Q2 2027 target holds. For the separate Helios II expansion, tenant agreements, permit instruments and power milestones would clarify its next construction stage. Each development should be attached to its own phase and capacity definition.
Contractors can use LVN Signal to follow construction intelligence and investigate the organizations behind prospective work. Helios currently combines an operating first phase with a documented construction expansion. The practical next step is to verify the buyer and issued scope for a specific package, then assess fit against crew capacity, testing capability and delivery requirements.
Reporting updated October 29, 2026. This refresh corrects the registered area total and distinguishes current contractor, financing and capacity scopes. Illustrations are AI-generated concepts; they do not document the actual site layout, equipment or construction progress.
Join 35,000+ Low Voltage Pros
Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.
