Access Control Permit Requirements in Fresno, California

Installing access control systems in Fresno requires understanding both state licensing regulations and local permit requirements. This guide covers the permit process through Fresno Building and Safety, BSIS licensing requirements, and what to expect for your installation project.

Quick Answer: Do You Need a Permit for Access Control in Fresno?

It depends on scope. Access control systems involving electrical work typically require an electrical permit from the City of Fresno Building and Safety Division. Simple low-voltage installations may have reduced requirements, but commercial projects generally need permits.

When Permits Are Required

Per California Building Code Section 105.1, permits are required when you "erect, install, enlarge, alter, repair, remove, convert or replace any electrical system." This typically includes:

  • New access control system installations
  • Card reader and credential reader installations
  • Electric strike and magnetic lock wiring
  • Biometric access devices
  • Door controller installations
  • Integration with fire alarm or security systems
  • Additions or modifications to existing systems

When Permits May Not Be Required

Limited exemptions may apply for:

  • Minor repairs not altering system configuration
  • Battery replacements
  • Like-for-like device replacements
  • Some standalone residential systems

Contact Fresno Building and Safety to confirm requirements for your specific project.

Licensing Requirements

Access control installations in California require proper state licensing:

License Type Issuing Agency Requirement
Alarm Company Operator (ACO) California BSIS Required for access control systems
C-7 Low Voltage California CSLB For low voltage electrical work

BSIS Alarm Company Operator License

The Bureau of Security and Investigative Services (BSIS) regulates alarm and access control companies in California. Requirements include:

  • Criminal background check through DOJ and FBI
  • Qualified Manager designation
  • $1,000,000 general liability insurance (for LLCs)
  • Live Scan fingerprinting
  • Renewal every two years

For complete California licensing information, see our California Low Voltage License Guide.

City of Fresno Permit Process

Step 1: Prepare Application

File an application with the Building and Safety Permit Counter. You can either:

  • Submit plans clearly detailing the scope of work for Plan Check review
  • Complete the Permit Affidavit Form with itemized fixture and equipment information

Step 2: Submit for Review

Submit through the Accela Citizen Access (ACA) portal or in person at the Building Permit Center.

Review Timelines:

  • Level 1 projects (electrical panels, simple systems): 2-3 business days completeness review, up to 3 business days plan check
  • Level 2-4 projects (commercial, complex): 21-28 business days

Step 3: Obtain Permit

Pay applicable fees and receive your permit. Express permits may be available for simple electrical projects (same-day processing).

Step 4: Installation and Inspection

Complete installation per approved plans and schedule inspection through the ACA portal.

Fresno County Projects

For projects in unincorporated Fresno County, apply through Fresno County Public Works and Planning:

  • Use the Citizens Portal to apply, track, pay, and schedule inspections
  • Building and Safety Division handles permits
  • Contact them for specific requirements in county jurisdiction

Permit Validity and Expiration

Timeframe Requirement
180 days Work must commence or permit becomes invalid
180 days Work cannot be suspended/abandoned this long
180 days Extension available with written request (before expiration)
1 year No activity makes permit null and void; new permit required at full fees

Residential vs. Commercial Projects

Residential Access Control

  • Simpler permit requirements for single-family homes
  • May qualify for express permits
  • Homeowners can pull permits for their own property
  • Must still use licensed contractors for installation

Commercial Access Control

  • Full plan review typically required
  • Must use licensed BSIS and CSLB contractors
  • Longer review timelines (Level 2-4 projects)
  • May require coordination with fire alarm systems
  • ADA/accessibility compliance review may apply

Contact Information

City of Fresno Building and Safety

Fresno County Building and Safety

  • Phone: (559) 600-4540
  • Website: fresnocountyca.gov
  • Citizens Portal for online applications

California BSIS

Pro Tips from the Field

  • Check jurisdiction: Confirm whether your project is in City of Fresno or unincorporated Fresno County—different permit processes apply.
  • Use express permits: Simple electrical projects may qualify for same-day express permits.
  • Start work promptly: Permits expire if work doesn't start within 180 days.
  • Request extensions early: If you need more time, submit written extension requests before permit expires.
  • Verify BSIS licensing: Both your company and subcontractors need proper BSIS credentials for access control work.
  • Online tracking: Use the ACA portal to track permit status and schedule inspections.

Stay Ahead of Permit Activity

Want to know when access control projects hit permits in Fresno before they reach bid boards?

LVN Signal monitors permit activity across California and alerts you to opportunities the moment they're filed.

→ Explore LVN Signal

Related Permit Guides

Tags

#permits
#california
#access-control
#licensing
#fresno

Join 35,000+ Low Voltage Pros

Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.