Fire Alarm Permit Requirements in Fort Collins, Colorado
Join Low Voltage Nation — Find project opportunities and showcase your company to thousands of industry professionals
Complete guide to fire alarm permit requirements in Fort Collins, Colorado. Learn about Poudre Fire Authority permits, contractor licensing, 2021 IFC compliance, and The Compliance Engine requirements.
Fire Alarm Permit Requirements in Fort Collins, Colorado
Quick Answer: Yes, Fort Collins requires fire alarm permits for new installations and system modifications. Fire alarm permits are obtained through Poudre Fire Authority (PFA), which enforces the 2021 International Fire Code. All fire alarm contractors must be licensed and insured to work within Fort Collins city limits or the State of Colorado.
Poudre Fire Authority Jurisdiction
Poudre Fire Authority (PFA) provides plan review, permitting, and inspection services for all fire alarm work within their jurisdiction, which includes:
- City of Fort Collins
- Town of Timnath
- Portions of Larimer County
- Portions of Weld County
PFA currently enforces the 2021 International Fire Code within these areas.
When Are Fire Alarm Permits Required?
Fire alarm permits are required for:
- New fire alarm system installations
- Modifications to existing fire alarm systems
- Panel replacements or upgrades
- System reprogramming affecting life safety
- Voice evacuation system installations
- Fire alarm/suppression integration
During the development and building permit processes, PFA determines if fire-protection system permits are required based on the locally adopted Fire and Building codes.
Contractor Licensing Requirements
All fire alarm contractors must meet these requirements:
| Requirement | Within Fort Collins | Outside City Limits |
|---|---|---|
| Contractor License | City of Fort Collins license required | State of Colorado license |
| Insurance | Required | Required |
| State Registration | DFPC registration for suppression | DFPC registration for suppression |
Colorado State Registration
The Colorado Division of Fire Prevention and Control (DFPC) requires registration for fire suppression system contractors. This includes individuals or companies that:
- Physically work on fire suppression systems
- Design fire suppression systems
- Test and inspect fire suppression systems
- Install any part of a fire suppression system
Design Requirements
The design of new fire alarm systems or alterations using performance-based design methods per NFPA 72 must be performed by a qualified professional.
Plan Review and Permit Process
- Submit Plans: Provide engineered fire alarm plans to PFA
- Plan Review: PFA reviews for code compliance
- Permit Issuance: Upon approval, permit is issued
- Installation: Licensed contractor performs work
- Inspections: Series of inspections during construction
- Final Approval: System approved for occupancy
Documentation Requirements
Fire alarm permit applications typically require:
- Engineered fire plans
- Riser diagrams
- Battery calculations
- Voltage drop calculations
- Sequence of operations
- Equipment cut sheets
Testing and Inspection Requirements
Important Change (Since January 2022): PFA no longer conducts fire sprinkler/alarm system tests. All inspection, maintenance, and testing must now be performed by a licensed contractor:
- Building/business owners select their own licensed contractor
- Owners are responsible for ensuring licensed contractors correct any deficiencies
- Test documentation submitted via The Compliance Engine® (TCE) through Brycer
Specific System Requirements
Per Fort Collins/PFA requirements:
- Two phone lines: Fire panels must have two working phone lines connected OR a cell unit
- Central station monitoring: Required for most commercial fire alarm systems
- NFPA 72 compliance: All systems must meet current NFPA 72 standards
Code Compliance
Fire alarm installations in Fort Collins must comply with:
- 2021 International Fire Code: Adopted by PFA
- NFPA 72: National Fire Alarm and Signaling Code
- Fort Collins Municipal Code Chapter 9: Fire Prevention and Protection
- NEC Article 760: Fire alarm circuit requirements
Residential vs. Commercial Requirements
Residential Fire Alarms
- Residential sprinkler systems require PFA plan review and inspections
- Smoke detectors required per building code
- Monitored systems may have additional requirements
Commercial Fire Alarms
- All commercial projects require formal plan review
- Series of inspections during construction
- Licensed contractors required for installation and testing
- Annual testing documentation required via TCE
Pro Tips from Contractors
- Verify jurisdiction first: PFA covers Fort Collins, but verify your project location is within their jurisdiction
- Use The Compliance Engine: PFA partners with Brycer for document submission—familiarize yourself with TCE
- Two phone lines or cell unit: Don't forget this Fort Collins requirement for fire panels
- DFPC registration: Ensure your state registration is current if doing suppression work
- Allow time for plan review: Commercial projects require formal review before permit issuance
Contact Information
Poudre Fire Authority - Fire Prevention
Phone: (970) 416-2891
Website: poudre-fire.org/contractors
PFA Development, Construction and Permitting
Website: poudre-fire.org/development
Fort Collins Building Services
Phone: (970) 416-2740
Website: fcgov.com/building/alarm
Colorado DFPC
Website: dfpc.colorado.gov
Stay Ahead of Permit Activity
Want to know when fire alarm projects hit permits in Fort Collins before they reach bid boards?
LVN Signal monitors permit activity across Colorado and alerts you to opportunities the moment they're filed.
Related Guides
Tags
Join 35,000+ Low Voltage Pros
Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.