Complete guide to structured cabling permit requirements in Bloomington, Minnesota. Learn about PLT licensing, Technology Systems Contractor requirements, and Minnesota DOLI regulations.

Structured Cabling Permit Requirements in Bloomington, Minnesota

Installing structured cabling and network infrastructure in Bloomington, Minnesota requires state licensing through the Minnesota Department of Labor and Industry. Located in the Minneapolis-St. Paul metro area and home to the Mall of America, Bloomington has significant commercial cabling needs. This guide covers everything contractors need to know about data cabling installations in this Twin Cities suburb.

Quick Answer: Do You Need a Permit for Structured Cabling?

State license required; permits depend on project scope. Minnesota requires a Power Limited Technician (PLT) license for individuals and a Technology Systems Contractor (TSC) license for companies performing low-voltage work including structured cabling. Building permits may be required for commercial projects, new construction, or work involving fire-rated assemblies. Standalone data cabling in existing spaces may be permit-exempt but still requires licensed contractors.

When Are Permits Required vs. Exempt?

State Licensing Always Required

  • All structured cabling work performed for compensation
  • Cat5e/Cat6/Cat6a cable installations
  • Fiber optic cable installations
  • Network infrastructure and patch panels
  • Telecommunications closet buildouts
  • WiFi access point installations
  • Cable tray and pathway installations

Building Permits May Be Required

  • New construction commercial cabling
  • Major tenant improvement projects
  • Penetrations through fire-rated assemblies
  • Exterior cable runs or building penetrations
  • Integration with fire alarm systems
  • Work in healthcare facilities

Typically Permit-Exempt (License Still Required)

  • Retrofitting existing spaces with data drops
  • Adding network outlets to existing pathways
  • Cable testing and certification
  • Equipment room rack installations

Minnesota State Licensing Requirements

The Minnesota Department of Labor and Industry administers electrical and low-voltage licensing under Minnesota Statutes Chapter 326B.

Power Limited Technician (PLT) License

Required for individuals performing low-voltage work:

  • 3 years of experience working for a licensed contractor
  • Must be registered as unlicensed worker during experience period
  • Experience must be in technology circuits and systems
  • Pass PLT licensing examination
  • Submit application through mn.gov/elicense

Technology Systems Contractor (TSC) License

Required for companies performing low-voltage work:

  • Must employ at least one licensed PLT or master electrician
  • Proof of liability insurance required
  • Workers compensation coverage required
  • Business registration with the state

PLT Work Scope Restrictions

PLTs cannot work on:

  • Class 2/3 circuits that control other electrical systems
  • Circuits in electrical cabinets with unprotected higher voltage
  • Hazardous locations
  • Critical care areas in healthcare facilities
  • Commercial fire alarm systems (requires fire alarm license)

Supervision Requirements

  • Unlicensed technicians can work under direct PLT supervision
  • Unlicensed workers must be registered with DOLI
  • Responsible licensed individual required for all projects

Code Compliance Requirements

Minnesota has adopted the 2023 National Electrical Code:

  • NEC Article 725: Class 1, Class 2, and Class 3 Remote-Control Circuits
  • NEC Article 770: Optical Fiber Cables and Raceways
  • NEC Article 800: Communications Circuits
  • Minnesota State Building Code Chapter 1315
  • 2024 Minnesota Commercial Energy Code (effective January 5, 2024)

Bloomington Building Department Process

Where to Apply

  • City of Bloomington Community Development
  • 1800 West Old Shakopee Road, Bloomington, MN 55431
  • Phone: 952-563-8920
  • Online permits through city portal

Typical Required Documents

  • Permit application
  • Floor plans showing cable pathways
  • Fire-rated penetration details (if applicable)
  • Contractor license documentation
  • Insurance certificates

Fees and Timeline

License/Permit TypeTypical FeeProcessing Time
PLT License (State)$75-$1502-4 weeks
TSC Company License (State)$150-$3004-6 weeks
Unlicensed Worker Registration$25-$501-2 weeks
Bloomington Building PermitVaries by scope5-10 business days

Fees current as of 2026. Contact Minnesota DOLI at 651-284-5012 for current licensing fees.

Mall of America and Large Commercial Considerations

Bloomington is home to significant commercial properties with specific requirements:

  • Mall of America has its own permit and vendor requirements
  • Large commercial properties may require coordination with property management
  • Data center work may have additional security clearance requirements
  • Healthcare facilities (like HealthPartners) have restricted areas for PLTs

Contractor Requirements Summary

To perform structured cabling work in Bloomington, Minnesota:

  • Technology Systems Contractor (TSC) license for company
  • Power Limited Technician (PLT) license for lead technician
  • All unlicensed workers registered with DOLI
  • General liability insurance
  • Workers compensation coverage
  • Minnesota business registration

Pro Tips

  • Register unlicensed workers: All technicians must be registered during their 3-year experience period
  • PLT restrictions: Know the boundaries - no fire alarm or healthcare critical care
  • 2023 NEC: Current code - ensure installations comply with latest requirements
  • Mall of America: Separate vendor credentialing process required
  • Supervision documentation: Keep records of supervision for unlicensed workers
  • Online licensing: Use mn.gov/elicense for all license applications

Stay Ahead of Cabling Projects

Want to know when structured cabling projects hit permits in Bloomington before they reach bid boards?

LVN Signal monitors permit activity across Minnesota and alerts you to opportunities the moment they are filed. Stop chasing—start catching.

Explore LVN Signal

Related Guides

Last updated: January 2026. Information verified against official sources. Minnesota requires PLT licensing for all low-voltage work—confirm current requirements with DOLI before starting projects.

#structured-cabling·#permits·#minnesota·#bloomington

Join 35,000+ Low Voltage Pros

Get weekly permit updates, tool deals, job opportunities, and industry news. No spam, unsubscribe anytime.